PE-11 Emergency power
Requires an uninterruptible power supply able to support either an orderly system shutdown or a transition to longer term alternate power when the primary power source is lost.
4
artefacts
1
held by a system
1
at each review
moderate
to go live
Physical access / facilities
where the evidence lives
teal = a system already holds it · olive = produced at each review
system holds itEvidence a system already holds
- Evidence of automated orderly shutdown configuration where that option is used · Physical access / facilities
periodic reviewEvidence produced at each review
- Maintenance, battery replacement and load test records · Physical access / facilities
governing documentDocuments that govern the control
- Uninterruptible power supply specification and the runtime it provides · Policy repository / GRC workspace
- Documented choice between orderly shutdown and transition to alternate power · Policy repository / GRC workspace
First move
Start with the 1 of 4 artefacts that already live in a system (Physical access / facilities); keep the periodic reviews but log each one as a dated record with a named reviewer.
Common gaps auditors find
- Battery runtime no longer matches the load after equipment was added
- Units never load tested, so actual runtime is unknown
- Supply protects servers while network and cooling equipment is unprotected