CCR 7155 Review risk assessments every three years and after material change

A risk assessment must be completed and documented before the processing begins, reviewed at least every three years, and updated as soon as feasible and within 45 calendar days of a material change, meaning one that creates new negative impacts, makes existing ones larger or likelier, or weakens safeguards. Assessments for processing begun before 1 January 2026 that continues afterwards are due by 31 December 2027. Assessments, original and updated, are kept while the processing runs and for five years after completion if that is later.

Source: CCPA/CPRA, CCR 7155. The statement above is our statement of the clause, read from the published text and cited so you can check it against the official text, not the instrument verbatim. Open CCPA/CPRA in the compliance library.

Applies only to a business that meets one of the thresholds in Cal. Civ. Code 1798.140(d).

3
artefacts
1
held by a system
0
at each review
moderate
to go live
Data governance / DLP tooling
where the evidence lives
teal = a system already holds it · olive = produced at each review. To go live: easy when half or more of the artefacts are already held by a system, moderate from a quarter to a half, hard below a quarter.

These are the artefacts auditors commonly ask for on this requirement, our guidance rather than text from the standard. Your assessor decides what is sufficient in your context, and asks for samples across the period when a report covers one.

system holds itEvidence a system already holds

  • Retention rule for assessment versions · Data governance / DLP tooling

periodic reviewEvidence produced at each review

none for this control

governing documentDocuments that govern the control

  • Assessment register with completion, review and next-review dates · Policy repository / GRC workspace
  • Change management trigger that flags material changes for reassessment within 45 days · Policy repository / GRC workspace

First move

Start with the 1 of 3 artefacts that already live in a system (Data governance / DLP tooling); keep the periodic reviews but log each one as a dated record with a named reviewer.

Common gaps auditors find

Do this for your whole sheet