CPS 234 para 35 Notify APRA of material incidents within 72 hours
The entity must tell APRA promptly, and at the latest within 72 hours of becoming aware, of any information security incident that either (a) had, or could have had, a material financial or non-financial effect on the entity itself or on the interests of its depositors, policyholders, beneficiaries or other customers (the impact limb), or (b) has already been notified to another regulator in Australia or overseas. A footnote covers incidents not already reported under CPS 231, SPS 231, CPS 232 or SPS 232, and counts domestic government agencies and international regulators as other regulators.
Source: APRA CPS 234, CPS 234 para 35. The statement above is our statement of the clause, read from the published text and cited so you can check it against the official text, not the instrument verbatim. Open APRA CPS 234 in the compliance library.
Applies to APRA-regulated entities.
These are the artefacts auditors commonly ask for on this requirement, our guidance rather than text from the standard. Your assessor decides what is sufficient in your context, and asks for samples across the period when a report covers one.
system holds itEvidence a system already holds
- Incident timeline records evidencing when the entity became aware · Regulator portal / correspondence
periodic reviewEvidence produced at each review
- Materiality assessment criteria and completed assessments per incident · Regulator portal / correspondence
- Register of notifications to other regulators that triggers APRA notification · Regulator portal / correspondence
governing documentDocuments that govern the control
- Notification procedure stating the 72-hour clock, who decides materiality and who submits to APRA · Policy repository / GRC workspace
- Copies of APRA notifications with timestamps of awareness and submission · Policy repository / GRC workspace
First move
Common gaps auditors find
- Clock started at confirmation of the incident instead of awareness
- Incidents reported to another regulator (for example the OAIC) but not to APRA
- Potential impact ignored because no actual harm occurred
Do this for your whole sheet
Paste the rows you run your controls from and get this mapping for every control at once, with the periodic-review ones flagged and a first move per row. No account for the first run.
Build my evidence sheetCPS 234 para 34 Internal audit assessment of third-party assurance · CPS 234 para 36 Notify APRA of material control weaknesses within 10 business days