A.7.11 Supporting utilities
Information processing facilities are to be protected against power cuts and other disruption caused by failures of supporting utilities. Purpose (stated in ISO/IEC 27002:2022): prevents loss, compromise or interruption of operations caused by failure of supporting utilities. As an Annex A reference control, it is compared with the controls determined in risk treatment (6.1.3 c) and recorded in the Statement of Applicability as included or excluded, with the justification and implementation status (6.1.3 d); implementation guidance is ISO/IEC 27002:2022 7.11.
Source: ISO/IEC 27001:2022, A.7.11. The statement above is our statement of the clause, read from the published text and cited so you can check it against the official text, not the instrument verbatim. Open ISO/IEC 27001:2022 in the compliance library.
Clauses 4 to 10 are the management-system requirements: none of them can be excluded when an organisation claims conformity. The 93 Annex A controls are a reference set: one may be excluded with a justification in the Statement of Applicability. Certification bodies assess conformity; the evidence lists here are what auditors commonly ask for, not a list the standard prescribes.
These are the artefacts auditors commonly ask for on this requirement, our guidance rather than text from the standard. Your assessor decides what is sufficient in your context, and asks for samples across the period when a report covers one.
system holds itEvidence a system already holds
- Alarm and monitoring configuration for utility failures · Physical access / facilities
periodic reviewEvidence produced at each review
- Maintenance and test records for UPS, generators, HVAC and other utility equipment against manufacturer specifications · Backup / DR tooling
- Capacity reviews of power, cooling and connectivity against business growth · Physical access / facilities
governing documentDocuments that govern the control
- Statement of Applicability entry for control A.7.11, showing inclusion or justified exclusion, implementation status and the risks it treats · Policy repository / GRC workspace
- Diagrams showing diverse feeds and routes for power and telecommunications where required · Policy repository / GRC workspace
First move
Common gaps auditors find
- Generators and UPS are not load-tested regularly
- Building management systems sit on the corporate network or are reachable from the internet
- A single power or telecom feed is a single point of failure
- Cooling capacity was not reviewed after adding equipment