A&A-06 Remediation

Track every audit finding on a risk-prioritised corrective action plan with named owners and due dates, and report remediation progress to the stakeholders accountable for closing it.

4
artefacts
0
held by a system
2
at each review
hard
to go live
Document repository
where the evidence lives
teal = a system already holds it · olive = produced at each review

system holds itEvidence a system already holds

none for this control

periodic reviewEvidence produced at each review

  • Closure evidence for findings marked complete · Document repository
  • Records of due-date extensions and who approved them · Document repository

governing documentDocuments that govern the control

  • The corrective action plan showing risk priority, owner and target date per finding · Policy repository / GRC workspace
  • Status reports issued to accountable stakeholders · Document repository

First move

This control is evidenced by people and documents, not systems. Put the document under version control with an owner and review date, and log each review as a record with reviewer and date. Do not try to automate it.

Common gaps auditors find

Do this for your whole sheet