DCS-03 Off-Site Transfer Authorization Policy and Procedures
Policies and procedures govern moving equipment, software or information to another site or a backup location, and each such move needs sign-off that is either written or can be verified cryptographically. Each year, and again after any significant change, the documents are revisited.
Source: CSA CCM v4.1, DCS-03. The statement above is our statement of the clause, read from the published text and cited so you can check it against the official text, not the instrument verbatim. Open CSA CCM v4.1 in the compliance library.
Version 4.1 adds 11 controls (among them API security, log sanitisation and a service bill of materials) and renumbers several domains. CSA accepts v4.0.x during its transition; if your STAR assessment is still on v4.0.1, check the numbering against it.
These are the artefacts auditors commonly ask for on this requirement, our guidance rather than text from the standard. Your assessor decides what is sufficient in your context, and asks for samples across the period when a report covers one.
system holds itEvidence a system already holds
- Gate or loading-dock logs showing equipment leaving the site · SIEM / log platform
periodic reviewEvidence produced at each review
- Sample of signed or digitally signed transfer authorisation forms or tickets · Ticketing / ITSM
- Shipping and chain-of-custody records matched to the authorisations · Document repository
- Policy review records, including updates after a site change · Policy repository / GRC workspace
governing documentDocuments that govern the control
- Asset relocation and transfer procedure naming who may authorise moves · Policy repository / GRC workspace
First move
Common gaps auditors find
- Equipment leaves the datacenter on verbal approval with no retained record
- Data transfers to alternate sites (for example backup tape rotation) not covered by the authorisation process
- Authorisers are not checked against an approved list
Do this for your whole sheet
Paste the rows you run your controls from and get this mapping for every control at once, with the periodic-review ones flagged and a first move per row. No account for the first run.
Build my evidence sheetDCS-02 Off-Site Equipment Disposal Policy and Procedures · DCS-04 Secure Area Policy and Procedures