EvidenceSheet

DCS-01 Physical and Environmental Security Policy and Procedures

The organisation keeps a set of policies and procedures covering physical and environmental security, formally approved, published to the people who must follow them, put into practice and assessed for effectiveness. They are reviewed and refreshed at least once a year and whenever a significant change occurs.

Source: CSA CCM v4.1, DCS-01. The statement above is our statement of the clause, read from the published text and cited so you can check it against the official text, not the instrument verbatim. Open CSA CCM v4.1 in the compliance library.

Version 4.1 adds 11 controls (among them API security, log sanitisation and a service bill of materials) and renumbers several domains. CSA accepts v4.0.x during its transition; if your STAR assessment is still on v4.0.1, check the numbering against it.

5
artefacts
0
held by a system
3
at each review
hard
to go live
Policy repository / GRC workspace
where the evidence lives
teal = a system already holds it · olive = produced at each review. To go live: easy when half or more of the artefacts are already held by a system, moderate from a quarter to a half, hard below a quarter.

These are the artefacts auditors commonly ask for on this requirement, our guidance rather than text from the standard. Your assessor decides what is sufficient in your context, and asks for samples across the period when a report covers one.

system holds itEvidence a system already holds

none for this control

periodic reviewEvidence produced at each review

  • Policy distribution or attestation records for datacenter and facilities staff · Physical access / facilities
  • Annual review log plus records of out-of-cycle reviews after events such as a new site or a major incident · SIEM / log platform
  • Results of physical security audits used to evaluate whether the policy is applied · Physical access / facilities

governing documentDocuments that govern the control

  • Approved physical and environmental security policy with owner, version and approval date · Policy repository / GRC workspace
  • Supporting procedures for facility access, environmental controls, asset movement and equipment decommissioning · Policy repository / GRC workspace

First move

No system holds this evidence for you: it is people and documents. Reminders and routing to the owner still save time. Put the document under version control with an owner and review date, and log each review as a record with reviewer and date.

Common gaps auditors find

Do this for your whole sheet

Paste the rows you run your controls from and get this mapping for every control at once, with the periodic-review ones flagged and a first move per row. No account for the first run.

Build my evidence sheet

CEK-21 Key Inventory Management · DCS-02 Off-Site Equipment Disposal Policy and Procedures